Frequently asked questions
FAQs- Click to read
- Wanneroo Road
- Lenore Road
- Badgerup Road
- Sydney Road
- Lindley Road
- Whiteman-Yanchep Highway
- Turkey Road (refer to Alternatives Assessment and Plan).
- planning rules and policies – alignment with State planning objectives, requirements, policies and plans (and an appropriate balance between competing objectives where these occur);
- advice provided by responsible agencies and local government – submissions from local government, State agencies or utilities providers; and
- planning matters raised during community consultation.
- number of objections or submissions of support alone;
- campaign‑style or duplicate submissions that do not raise new planning-related matters;
- issues unrelated to land use planning considerations; and
- matters already determined under separate approvals.
What is the land zoned under the MRS?
The transmission line and steel poles traverse land zoned Industrial, Rural – Water Protection, Urban Deferred, Rural and reserved Primary Regional Roads, Other Regional Roads, Regional Open Space, Public Purposes and State Forests under the MRS.
Why is this proposal being advertised?
To obtain community feedback on the proposed development, as part of the assessment process. The proposal is being advertised pursuant to clause 41(1)(a) of the MRS.
What is the role of Department of Planning, Lands and Heritage (DPLH) in this project?
DPLH officers will assess the application and make recommendations to the WAPC under the MRS.
Who is the decision maker for this development application?
The development application will be determined by the Western Australian Planning Commission (WAPC) under Part 10 of the Metropolitan Region Scheme (MRS).
I provided my comment on this proposal to Western Power. Do I need to provide my feedback again?
Yes. You may have previously provided feedback on the proposal as part of a separate consultation process undertaken by Western Power, under Section 60 of the Electricity Corporations Act 2005 for certain works exempt from planning laws.
This development application is now being assessed under the MRS and any feedback on the application must be submitted separately via the online survey, email or via post to: Department of Planning, Lands and Heritage, Land Use Planning – Metro North - East Wanneroo team, Locked Bag 2506, Perth, 6001.
Why does the Clean Energy Link – North need to be built?
The Clean Energy Link – North is a major transmission upgrade to strengthen the network through Perth’s northern suburbs to enable more clean energy, generated from renewable energy sources often located outside the metropolitan area, to flow to Perth to meet growing community and industry demand.
Where will the transmission line and power poles be located?
The proposed transmission line and steel poles are to be largely located within existing easements and road reserves where possible. Parts of the transmission line and steel poles will traverse or be positioned on Crown land. The transmission line alignment is depicted in the Applicant Development Plans under Key Documents.
How many power poles will be installed?
175 steel poles (approximately 18.5 to 25 metres in height) will be installed.
How will the alignment be assessed?
The applicant has submitted a Development Application Report in support of the proposed alignment. The WAPC is to consider if the proposal is consistent with the statutory planning framework, including State Planning Policies, MRS and the WAPC Development Control and Operational Policies, and consider feedback from relevant State and local government agencies and the community.
What alternative routes were considered?
A total of seven alignment options were considered by Western Power, including:
Why isn't the entire line underground?
Undergrounding the power line would significantly increase costs, require more clearing and trenching, sterilise land for future development and increase construction impacts (refer to Alternatives Assessment and Plan for further details).
Have visual impacts been considered?
The applicant’s Development Application Report states that the proposed alignment has been sited along existing road corridors to minimise visual amenity impacts on the locality and is considered consistent with the typical visual character of roadway environments.
What are the environmental impacts on flora and fauna?
The proposal has the potential to result in the clearing of up to 14 ha of native vegetation, including approximately 0.29 ha of the Commonwealth-listed Banksia Woodlands of the Swan Coastal Plain Threatened Ecological Communities (Endangered) (Banksia Woodlands TEC), which is inclusive of State-listed Priority Ecological Communities.
The application has been referred to the Department of Water and Environmental Regulation, Department of Biodiversity, Conservation and Attractions and the City of Wanneroo for comment.
What standards apply to electromagnetic fields?
Electric and Magnetic Fields (EMF) are carefully considered in the planning, location, and operation of Western Power network assets. Western Power is guided by Australian and international health authorities and takes a precautionary approach in line with the Energy Network Australia EMF Management Handbook. This includes applying industry best practice methods to its engineering and design solutions to reduce or mitigate EMF exposure.
What information will the WAPC consider in its decision?
In determining applications under the MRS, the WAPC must have regard to the planning framework and will consider a wide range of planning matters – issues that relate to land use, development, transport, environment and planning policy and the realisation of strategic plans. Its decision-making takes into account:
What does not usually influence a WAPC decision?
The following matters are acknowledged for transparency, but they do not usually influence a WAPC decision:
Will I be advised about the application outcome?
If you agree to be contacted when you make your online submission, you will be notified of the application outcome.
Where can I get more information?
While public advertising is open, the development application can be viewed on this page or in person at the Department’s Perth offices, Level 2, 140 William Street, Perth (by appointment).
Appointment requests and any enquiries related to the application should be directed to the Department, either by email to ewdsp@dplh.wa.gov.au or by phone to 6551 8002.